Acts and Regulations

2020, c.8 - Building Code Administration Act

Full text
Building and demolition permits
6A building inspector shall issue a building permit or a demolition permit, as the case may be, if the following conditions are fulfilled:
(a) the owner or a person acting on behalf of the owner makes an application in accordance with a building by-law or a regulation;
(b) a development officer has granted an approval with respect to the work under subsection 108(0.1) of the Community Planning Act; and
(c) the owner or a person acting on behalf of the owner pays the fees prescribed by a building by-law or a regulation.
2021, c.44, s.31
Building and demolition permits
6A building inspector shall issue a building permit or a demolition permit, as the case may be, if the following conditions are fulfilled:
(a) the owner or a person acting on behalf of the owner makes an application in accordance with a building by-law or a regulation;
(b) a development officer has approved the construction or demolition under subsection 108(1) of the Community Planning Act; and
(c) the owner or a person acting on behalf of the owner pays the fees prescribed by a building by-law or a regulation.
Building and demolition permits
6A building inspector shall issue a building permit or a demolition permit, as the case may be, if the following conditions are fulfilled:
(a) the owner or a person acting on behalf of the owner makes an application in accordance with a building by-law or a regulation;
(b) a development officer has approved the construction or demolition under subsection 108(1) of the Community Planning Act; and
(c) the owner or a person acting on behalf of the owner pays the fees prescribed by a building by-law or a regulation.